After upgrading five eastbound bridge approaches on State Route 260 last fall, the Arizona Department of Transportation is returning this month to replace and repave the approaches to three westbound bridges between mileposts 272-277, approximately 20 miles east of Payson.
Motorists traveling along SR 260 should allow extra travel time and be aware that westbound traffic will be shifted to the eastbound lanes, which will become a two-way roadway through the five-mile work zone, beginning on Tuesday, March 24. A 10-foot width restriction will be in place throughout construction and drivers should be aware of heavy traffic during peak travel times.
The $2.9 million improvement project, which is expected to be completed in August, includes the removal of the existing bridge approaches and departure slabs, repaving the roadway at the bridge approaches, guardrail reconstruction and the replacement of existing pavement markings.