CHINO VALLEY — Overnight paving work has been scheduled on State Route 89 between Prescott and Chino Valley this weekend starting Friday night, June 26 through Sunday, June 28, weather permitting. Work will take place on the south end of the project at the new Deep Well Ranch Road roundabout.
Motorists traveling on SR 89 between 4 p.m. and 5 a.m. Saturday, June 27 and Sunday, June 28 (no impacts on Friday night) should allow extra travel time through the work zone. A detour will be in place redirecting traffic in both directions onto the new Deep Well Ranch Road to Ruger Road.
Delays of up to 15 minutes at a time are expected. Flaggers and law enforcement will be present to guide motorists through the detour safely.
Upon completion of the $17 million project, ADOT will expand the two-lane roadway to a four-lane divided highway along a five-mile segment of SR 89 (mileposts 320-325) between Road 4 South in Chino Valley and Deep Well Ranch Road in Prescott, just north of the SR 89/SR 89A junction. The project is scheduled to be complete by August.