Overnight work scheduled on SR 89 between Prescott and Chino Valley next week

PRESCOTT/CHINO VALLEY – Traffic on State Route 89 between Prescott and Chino Valley (mileposts 320-325) will be required to stop intermittently next week to allow trucks to safely cross the highway and crews to relocate temporary concrete barrier along the roadway.

Overnight work will begin on Monday, July 14 through Thursday, July 17, between 8 p.m. and 5 a.m. each night.

Drivers can expect intermittent closures for dirt hauling and delays of up to 15 minutes at a time.

The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to allow additional time to reach their destinations and to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

Work on SR 89 in Prescott for the next two weeks

PRESCOTT – Crews will be present on State Route 89 (White Spar Road) in Prescott over the next two weeks to complete miscellaneous work on the improvement project.

There will be intermittent lane restrictions between 6 am. and 6 p.m. Monday through Friday through July 3. The speed limit will be reduced to 25 mph through the work zone.

Also, overhead utility work is scheduled Monday, June 23 through Wednesday, June 25 between 5 a.m. and 6 p.m. Drivers can expect a single lane restriction.

ADOT advises drivers and bicyclists to proceed through the work zone with caution, comply with the reduced speed limit and be alert for construction equipment and personnel.

Dirt haul on SR 89 between Prescott and Chino Valley scheduled this week

Traffic on State Route 89 between Prescott and Chino Valley (mileposts 320 to 322) will be required to stop intermittently this week to allow trucks to safely cross the highway.

The hauling operation will take place from 8 p.m. to 5 a.m. Monday and Tuesday, June 16-17, with intermittent closures for dirt hauling. Drivers can expect delays of up to 15 minutes at a time.

The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to allow additional time to reach their destinations and to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

Final paving on SR 89 on White Spar Road in Prescott next week

adot-logo3ADOT is nearing completion of a pavement maintenance on White Spar Road in Prescott which began April 10.

Final pavement will be placed next week on the new roadway on State Route 89 (White Spar Road) in Prescott on Wednesday and Thursday, June 4 and 5 between 7 a.m. and 6 p.m.

As paving activity occurs, drivers can expect delays of up to 15 minutes. Once paving is complete, crews will return in 30 days for final striping.

The speed limit will be reduced to 25 mph through the work zone. ADOT advises drivers and bicyclists to proceed through the work zone with caution. Comply with the reduced speed limit and be alert for construction equipment and personnel.

Improvement project on SR 89 on White Spar Road in Prescott nears completion

adot-logo3Crews will begin paving the roadway on State Route 89 (White Spar Road) in Prescott starting on Tuesday, May 20.

Next week, paving work will occur Tuesday through Thursday, May 20 to May 22, and be off the road on Friday, May 23 in time for the Memorial Day weekend.

During paving activities drivers can expect delays of up to 15 minutes over the next two weeks. Work hours are 7 a.m. and 6 p.m., Monday through Friday.

The speed limit will be reduced to 25 mph through the work zone. ADOT advises drivers and bicyclists to proceed through the work zone with caution, comply with the reduced speed limit and be alert for construction equipment and personnel.

Bridge work on SR 260 starts tomorrow east of Payson

PRESCOTT – The Arizona Department of Transportation will begin a bridge rehabilitation project on Tuesday, April 29 along a 10-mile stretch of State Route 260 (mileposts 267-277), approximately 17 miles east of Payson.

This $2.9 million project consists of reconstructing the existing bridge approaches of eight structures on the eastbound and westbound roadways. Work also includes milling and replacing the existing pavement at the bridge approaches, guardrail reconstruction and the replacement of existing pavement markings.

Work will begin tomorrow, April 29 at 6 a.m. in two locations, and will be in place for the next three months. Drivers can expect the eastbound lanes, at both locations, to be closed and traffic switched over to one of the westbound lanes creating a two-way roadway. Work hours are 6 a.m. to 4 p.m. Monday through Friday.

The first will be at the Tonto Creek Bridge (mileposts 267-268) near Kohl’s Ranch Road and the second will start at the Christopher Creek Campground (mileposts 272 -277) and work eastbound for five miles.

Delays are possible and drivers need to allow extra travel time to reach their destinations. The closures and detour will be in effect for the next three months.

The work zone will be clearly marked by temporary barricades and signage. ADOT advises drivers to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

Veteran hospital in Phoenix highlighted as an example of leaving veterans to die.


Photo Phoenix Business Journal

Photo Phoenix Business Journal

PHOENIX – According to a CNN report, the Carl T. Hayden VA Hospital in Phoenix had two waiting lists which left as many as 40 veterans waiting for care dead. A doctor alleges that the records that a waiting list even existed were shredded. The accusations by CNN reporting have recently prompted a Senate hearing on the matter.

The Phoenix VA Health Care web site states:

“Honoring America’s Veterans with quality health care services, part of the largest integrated health care system in the U.S.”

dr-foote-right-01CNN interviewed Dr. Sam Foote who retired from the VA Center in Phoenix after 24 years. Dr. Foote alleges that the VA kept two list of appointments. One he called a sham list that showed veterans were being seen in 14-days while the other secretive list were those veterans awaiting appointments.

CNN reported that records that would indicate that such a list existed were shredded in an apparent cover-up.

“The scheme was deliberately put in place to avoid the VA’s own internal rules,” said Foote in Phoenix. “They developed the secret waiting list,” said Foote, a respected local physician.

The CNN report covers the plight of U.S. Navy veteran Thomas Breen who died waiting for simple tests that could have saved his life.

Republican Senators John McCain and Jeff Flake and Democratic Representatives Raul Grijalva and Kyrsten Sinema have called for hearings. Senator McCain sent a letter to VA Secretary Eric Shinseki asking about the alleged waiting lists and if at least 40 veterans died as a result of the waiting lists, among other things.

According to CBS 5 in Phoenix, Sinema said:

“I am deeply disturbed by the allegations that delays in care and false record-keeping at the Phoenix VA Medical Center may have caused the deaths of Arizona veterans. We need a thorough investigation that holds those responsible for veteran deaths accountable.”

The report from Phoenix led KSDK in St. Louis to do a report on Albert Boyd—one of their local decorated Vietnam veterans.

When Boyd learned of the CNN report that the Phoenix VA had a secret set of records that hid its backlog of disability claims, he said it reminded him of his own struggles with the VA. Two years ago he hired a lawyer to fight his benefits battle with the Department of Veterans Affairs. He doesn’t expect a quick resolution.

“Delay, deny, until you die. That’s what the veterans are saying now,” said Boyd.

Delays in the VA Health Care system are, unfortunately, nothing new. The delay until you die concept was developed around illnesses Vietnam veterans complained about concerning the use of Agent Orange.

Agent Orange was a defoliant manufactured for the U.S. Department of Defense primarily by Monsanto Corporation and Dow Chemical. The chemical was sprayed without restrictions between 1961 to 1971.

One Williams veteran told me that they would have to cover up in their jackets with their hoods in an effort to keep the chemical off of their bodies.

Like the Agent Orange issue, returning veterans began reporting symptoms of what has come to be known as Gulf War syndrome. The VA at first denied the existence of any disease only looking into the issue a few years later after media publicity led to documentaries and a 1998 television dramatization, Thanks of a Grateful Nation.

Screenshot of Phoenix VA web site.

Screenshot of Phoenix VA web site.

Pavement work scheduled on State Route 89 on White Spar Road

Delays of up to 15 minutes expected for the next two weeks

Crews will begin milling the asphalt on State Route 89 on White Spar Road in Prescott starting on Thursday, April 10, according to the Arizona Department of Transportation.

Over the next two weeks drivers can expect delays of up to 15 minutes at a time between the hours of 7 a.m. and 6 p.m., Monday through Friday.

Once the asphalt has been removed, crews will need time to build the road up in areas along the project and as a result, the existing roadway will be a dirt surface until the road is ready for pavement.

The speed limit will be reduced to 25 mph through the work zone. ADOT advises drivers and bicyclists to proceed through the work zone with caution, comply with the reduced speed limit and be alert for construction equipment and personnel.

The work zone will be clearly marked by temporary barricades and signage.

Night work this week on State Route 89 between Prescott and Chino Valley

Barrier and restriping work between 7 p.m. and 5 a.m. tonight through Thursday night

The Arizona Department of Transportation has begun placing temporary concrete barrier and restriping the roadway for the widening project on State Route 89 between Chino Valley and Prescott.

The work will take place over three nights between 7 p.m. and 5 a.m. starting tonight through Thursday, March 27. Drivers can expect minimal delays during work hours.

In addition to this night work, the project’s regularly scheduled work hours are Monday through Thursday between 6 a.m. and 6 p.m.

ADOT advises drivers and bicyclists to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.

Construction to widen State Route 89 between Prescott and Chino Valley begins

Four-lane divided highway to improve travel times for drivers

PRESCOTT – The Arizona Department of Transportation will start a widening project this week on State Route 89 in an effort to improve travel times and enhance safety for motorists traveling between Chino Valley and Prescott.

Upon completion of the $17 million project, ADOT will expand the two-lane roadway to a four-lane divided highway along a five-mile segment of SR 89 (mileposts 320-325) between Road 4 South in Chino Valley and Deep Well Ranch Road in Prescott, north of the SR 89/SR 89A junction.

The new southbound roadway will be parallel to the existing highway between Prescott and Chino Valley and will include the construction of two roundabouts at Deep Well Ranch Road and Kalinich Avenue.

Project work hours are Monday through Thursday from 6 a.m. to 6 p.m. and minimal impacts to the traveling public are expected as the majority of the work will not be performed on the existing roadway.

This project is expected to be completed by summer 2015.

ADOT advises drivers to proceed through the work zone with caution, comply with the reduced speed limit, and be alert for construction equipment and personnel.