Closures scheduled in conjunction with I-17, I-40 and Beulah Boulevard improvement project

FLAGSTAFF – Flagstaff-area drivers should plan for closures while deck work continues on four Interstate 40 bridges that carry traffic over I-17 and Beulah Boulevard. The Arizona Department of Transportation advises motorists to use detour routes and allow extra travel time while the following restrictions are in place:

  • The closure of the ramp from southbound I-17 to eastbound I-40 will remain in place around the clock through Wednesday, October 17. Detour: Use southbound I-17 to the J.W. Powell/ I-17 interchange, then travel north on I-17 to eastbound on I-40.
  • Northbound Beulah Boulevard will be closed from 8:30 p.m. Sunday, October 21, to 5 a.m. Monday, Oct. 22, and from 10:30 p.m. Monday, October 22, to 5 a.m. Tuesday, October 23. Detour: Travel south to the J.W. Powell/ I-17 interchange, then north on I-17 to Forest Meadows Street and west to Beulah Boulevard.
  • Southbound Beulah Boulevard will be closed from 10:30 p.m. Tuesday, October 23, to 5 a.m. Wednesday, October 24, and from 10:30 p.m. Wednesday, October 24, to 5 a.m. Thursday, October 25. Detour: Travel north to Forest Meadows Street, east to I-17 and south onto southbound I-17 to the J.W. Powell/I-17 Interchange, then north on Beulah Boulevard.

Work to repair and replace the decks on the four bridges began eight months ago and is scheduled for completion later this year. Learn more on the project webpage. ADOT advises drivers to slow down in the work zone, follow posted detour routes and use caution around construction personnel and equipment.

Schedules are subject to change based on weather and other unforeseen factors. For more information, please call the ADOT Project Information Line at 855.712.8530 or email Projects@azdot.gov. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except when driving.

Flagstaff Traffic Alert: Lane closures planned on Beulah Boulevard under Interstate 40

FLAGSTAFF – Arizona Department of Transportation crews are scheduled to set lane restrictions on Beulah Boulevard under the I-40 bridge overpass in Flagstaff. Drivers are advised to allow extra travel time as crews will have lane closures in both directions from 8 p.m. Thursday, April 12, to 5 a.m. Friday, April 13. One lane in each direction will remain open at all times. Additionally, lane widths will be restricted to 11 feet throughout the construction project.

These lane closures and width restrictions are necessary for crews to begin bridge deck replacement and repair work at the I-17 and I-40 interchange in Flagstaff. This project will replace three bridge decks and approach slabs, increase the bridge cross slopes and retrofit one bridge deck with an overlay. The project will also include guardrail and paving work.

Construction began in February 2018 and the majority of the work is scheduled to be complete by the end of the year.

ADOT is scheduled to host informational sessions for the public from 5:30 to 7 p.m. on April 9, May 8, June 12 and July 10. These open houses will be at ADOT’s facility at 1901 S. Milton Road in Flagstaff. Project team members will be available to provide information and answer questions on the construction schedule and traffic impacts.

What to Expect:

  • Construction seven days a week with both day and night work, according to project phasing
  • Overnight, one-direction closures on Beulah Boulevard beneath I-40
  • Rolling night closures of I-17, according to phasing
  • Ramp closures
  • The southbound I-17 to eastbound I-40 ramp is scheduled to be closed in two-week increments at the end of June, end of July and end of October
  • The northbound I-17 to westbound I-40 ramp is closed through December

Schedules are subject to change based on weather and other unforeseen factors. For more project information, please visit www.azdot.gov/FlagstaffTI. For questions or comments, please contact Mackenzie Kirby, ADOT Northcentral District Community Relations Project Manager at 928-525-6494 or mkirby@azdot.gov. For more information, please call the ADOT Project Information Line at 855.712.8530 or email Projects@azdot.gov. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except when driving.