Plan for 40-day closure of A-1 Mountain Road Bridge over Interstate 40 in Flagstaff scheduled for May 2 – June 10

The Arizona Department of Transportation advises drivers to plan for an extended closure of the A-1 Mountain Road Bridge over Interstate 40 (exit 190) from midnight Monday, May 2, to 11 p.m. Friday, June 10, as work continues on the bridge replacement project.

  • DETOUR TO A-1 MOUNTAIN ROAD: Drivers traveling eastbound on I-40 traffic will take Exit 191 to turn around and travel westbound on I-40 to access A-1 Mountain Road.
  • DETOUR TO EASTBOUND I-40: Drivers on A-1 Mountain Road will first travel west on I-40 and exit Hughes Avenue (Exit 185- Bellemont) to turn around and proceed eastbound on I-40.

Drivers should proceed through the work zone with caution, slow down and watch for construction personnel and equipment.

For more information, visit https://azdot.gov/i40-A1-Mountain

Bridge rehabilitation project on I-40 near Ash Fork is underway

ASH FORK – Motorists traveling along Interstate 40 near Ash Fork should be prepared for lane restrictions now through early October for a bridge rehabilitation project.

The work includes rehabilitating 10 bridge decks between the West Ash Fork traffic interchange and the East Ash Fork traffic interchange, which is between mileposts 143 and 148). This week crews have begun installing temporary traffic control barriers. The crew is also installing detour crossovers prior to working on the eastbound bridges.

Working hours are Monday through Thursday, 7 a.m. to 5 p.m. and Fridays 7 a.m. to noon. One lane will remain open in each direction, the speed limit will be reduced and drivers should be alert for construction vehicles and flaggers. A 12-ft. width restriction is also in place.

This fall crews are scheduled to be completed with work on the eastbound bridges. The $5 million project will then go in to a winter shutdown until spring 2015, and then warmer weather will allow for work to continue on the westbound bridges.

ADOT works to inform the public about planned highway restrictions, but there is a possibility that unscheduled closures or restrictions may occur. Weather can also affect a project schedule.

Bridge work starting on I-40 in Winslow

Drivers should expect narrowed lanes and reduced speed limits on I-40 through Winslow

PHOENIX – The Arizona Department of Transportation begins a project on Monday, March 31 to reconstruct Interstate 40 bridges at Ruby Wash, Maple Street and Transcon Lane in Winslow.

The east- and westbound bridges at each location, six total, will be improved during the $3.8 million dollar project. Work includes replacing the bridge decks, new asphalt and some guardrail and drainage improvements.

All six bridges will be under construction simultaneously and I-40 will be narrowed to one lane between mileposts 254 and 257 through fall 2014, when the project is anticipated to be completed. There will be narrow traffic lanes, wide load restrictions and a reduced speed limit through the work zone.

In addition to the interstate restrictions, there are local restrictions as well. Maple Street, which runs underneath I-40, will be closed for six months. Detour signs will be posted for alternate routes during its closure. Also, Transcon Lane, which also runs under I-40, will have intermittent lane closures, but will remain open to traffic. Work hours will be 7 a.m. to 5 p.m. Monday through Friday.

ADOT advises drivers to proceed through the work zone with caution, slow down, and be alert for construction equipment and personnel.