Work at Interstate 40 and Bellemont traffic interchange continues this week

BELLEMONT – The Arizona Department of Transportation is scheduled to continue paving at the Bellemont traffic interchange next week as part of the improvement project on Interstate 40 from Parks to Riordan.

ADOT advises drivers to allow extra travel time while work occurs on the eastbound ramps (Exit 185) as follows:

· Tuesday, Sept. 26, from 6 a.m. to 3 p.m.
· Thursday, Sept. 28, from noon to 6 p.m.
· Friday, Sept. 29, from 4:30 a.m. to noon.

Motorists can use the interchanges at Parks (milepost 178) and A-1 Mountain (milepost 190) to travel between eastbound I-40 and Bellemont. Signs will mark the detour routes. The Bellemont bridge over I-40 will remain open at all times, and no restrictions are scheduled on the westbound I-40 ramps.

For more information about this project, visit azdot.gov/I40Paving.

Drivers should use caution and watch for construction personnel and equipment.

Schedules are subject to change based on weather and other unforeseen factors. For more information, please call Coralie Cole, ADOT community relations project manager, at 602.501.4899 or ccole@azdot.gov. For real-time highway conditions statewide, visit the ADOT Traveler Information site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.

Interstate 40 eastbound ramp work at Bellemont begins tomorrow

BELLEMONT – The Arizona Department of Transportation is ahead of schedule for ramp repairs at the Bellemont traffic interchange and will begin reconstructing the eastbound Interstate 40 on- and off ramps at Exit 185 early Tuesday, Aug. 22.

Work on the westbound ramps is anticipated to be completed early Tuesday morning, and the ramps will be reopened for travel at 7 a.m. Once the westbound ramps are open, the eastbound on- and off-ramps at Bellemont will be closed for construction from 7 a.m. Tuesday, Aug. 22, to 6 p.m. Thursday, Aug. 31. The Bellemont bridge over I-40 will remain open at all times.

Motorists can use the interchanges at Parks (milepost 178) and A-1 Mountain (milepost 190) to travel between eastbound I-40 and Bellemont. Signs will mark the detour routes.

Ramp repairs are anticipated to be completed in time for the Labor Day weekend with no restrictions to the Bellemont area.

The ramp reconstruction is part of a larger project underway between Parks and Riordan that includes paving, new guardrail and minor bridge repairs at the Parks, Bellemont and A-1 Mountain traffic interchanges. Please visit the project website for more information at: azdot.gov/I40Paving.

Drivers should use caution and watch for personnel and equipment while construction is underway. Please allow for extra time for travel.

Schedules are subject to change based on weather and other unforeseen factors. For more information, please call Coralie Cole, ADOT senior community relations officer, at 602.501.4899 or ccole@azdot.gov. For real-time highway conditions statewide, visit the ADOT Traveler Information site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.

Interstate 40 westbound ramp work at Bellemont begins Monday

BELLEMONT – The Arizona Department of Transportation will begin reconstructing the westbound Interstate 40 on- and off-ramps at Bellemont (exit 185) early Monday, August 14.

To accommodate this work, the westbound on- and off-ramps at Bellemont will be closed from 5 a.m. Monday, August 14 to 6 p.m. Friday, August 25. The Bellemont bridge over I-40 will remain open at all times.

Motorists can use interchanges at Parks (milepost 178) and A-1 Mountain (milepost 190) to travel between westbound I-40 and Bellemont. Signs will mark the detour routes.

After work ends on the westbound ramps at Bellemont, crews will begin reconstructing the interchange’s eastbound on- and off-ramps.

The ramp reconstruction is part of a larger project underway between Parks to Riordan that includes paving, new guardrail and minor bridge repairs at the Parks, Bellemont and A-1 Mountain traffic interchanges. Please visit the project website for more information at: azdot.gov/I40Paving.

Drivers should use caution and watch for personnel and equipment while construction is underway. Please allow for extra time for travel.

Schedules are subject to change based on weather and other unforeseen factors. For more information, please call Coralie Cole, ADOT senior community relations officer, at 602.501.4899 or ccole@azdot.gov. For real-time highway conditions statewide, visit the ADOT Traveler Information site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.

Paving scheduled on Interstate 40 near Interstate 17 junction next week

FLAGSTAFF – Motorists traveling eastbound on Interstate 40 to Flagstaff should allow extra time while paving continues near the I-17 junction. Paving is scheduled from 2 a.m. to noon both Tuesday, August 8, and Wednesday, August 9. A single-lane restriction will be in place to accommodate work between mileposts 195 and 197, located one mile west of Butler Avenue.

Drivers should use caution and watch for construction personnel and equipment while paving is underway.

Schedules are subject to change based on weather and other unforeseen factors. For more information, call the ADOT Project Information Line at 855.712.8530 or email Projects@azdot.gov. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.

Traffic switch next week for Interstate 40 work west of Williams

WILLIAMS – Drivers heading eastbound on Interstate 40 toward Williams and Flagstaff will use one of the westbound lanes for five miles starting Monday, August 7, while Arizona Department of Transportation crews begin rebuilding the eastbound section of highway.

The project, occurring between mileposts 156 and 161, will rebuild the roadway from the ground up, including laying a new foundation. This work will be a long-term fix for the winter-weather damage this stretch has seen through the years.

This past week, crews have been building a temporary road across the median at each end of the project for eastbound drivers which will create one lane in each direction on the westbound side of I-40. The traffic switch will occur early Monday morning and remain in place through the fall.

Motorists traveling in the area should slow down and plan for extra travel time through the project area.

Because of the critical nature of I-40 for truckers and travelers, ADOT worked to get this $34 million project started this summer.

In addition to this project, crews continue to repave 12 miles of I-40 in each direction closer to Flagstaff between mileposts 179 and 191. That $13.9 million project is about halfway complete.

Crews will also be doing minor paving repairs in the morning hours on August 8 and 9 on eastbound I-40 near the I-17 junction approaching the Butler Avenue exit.

For more information on this and other paving projects along I-40, visit azdot.gov.

Paving on Interstate 40 west of Williams begins Monday

WILLIAMS – To address the beating a section of Interstate 40 just west of Williams has taken over many winters, the Arizona Department of Transportation will begin reconstructing five miles of roadway in both directions on Monday, July 24.

The $34 million project, which will start with the eastbound direction between mileposts 156 and 161, will literally rebuild the roadway from the ground up, including laying a new foundation.

Drivers heading east on I-40 toward Williams and Flagstaff will cross the median on a temporary road and share lanes with westbound I-40 traffic through the project area, with one lane of travel in each direction. Drivers should slow down and budget for extra travel time.

Crews will rebuild the westbound side of the interstate next summer.

ADOT is currently repaving 12 miles of I-40 in each direction closer to Flagstaff between mileposts 179 and 191. The $13.9 million project, which is about halfway complete, includes minor bridge repairs at the Bellemont, A-1 Mountain and Riordan overpasses as well as new guardrail.

Drivers should use caution and watch for construction personnel and equipment while paving is underway.

Schedules are subject to change based on weather and other unforeseen factors. For more information, please call Coralie Cole, ADOT senior community relations officer, at 602.501.4899 or email: ccole@azdot.gov. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.

Paving scheduled on Interstate 40 near I-17 Junction Thursday, July 20

FLAGSTAFF – Motorists traveling eastbound on Interstate 40 to Flagstaff should allow extra time while paving is underway near the I-17 Junction. Construction is scheduled from 4 a.m. to 2 p.m. Thursday, July 20. A single-lane restriction will be in place to accommodate work between mileposts 195 and 197, located one mile west of Butler Avenue.

Drivers should use caution and watch for construction personnel and equipment while paving is underway.

Plan for lane restrictions and possible closure of eastbound Interstate 40 near Bellemont early Thursday, July 13

BELLEMONT – Drivers could be delayed on eastbound I-40 near Bellemont early Thursday, and Mother Nature is to blame. A recent lightning strike damaged a 90-foot pine tree adjacent to travel lanes at milepost 186, and the tree must be removed for safety.

Work is scheduled to occur on eastbound I-40 from 6 to 11 a.m. Thursday, July 13. I-40 will be narrowed to one lane; however, a full closure of eastbound travel lanes might be necessary to prevent debris from entering the roadway.

Drivers should plan to slow down and watch for construction personnel and equipment, as well as law enforcement officers who will be on site to assist with traffic control.

Schedules are subject to change based on weather and other unforeseen factors. For more information, please call the ADOT Project Information Line at 855.712.8530 or email Projects@azdot.gov. For real-time highway conditions statewide, visit ADOT’s Traveler Information Site at www.az511.gov, follow ADOT on Twitter (@ArizonaDOT) or call 511, except while driving.

ADOT moves forward with project replacing pavement on 12 miles of I-40

FLAGSTAFF – With a contractor selected, the Arizona Department of Transportation is moving forward with a $13.9 million project to add new pavement to 12 miles of Interstate 40 between Flagstaff and Williams.

Meeting in Flagstaff on Friday, April 21, the State Transportation Board approved a contract for the project with FNF Construction. A schedule will be set in the coming weeks.

The work in both directions between Parks and Riordan, milepost 179 to 191, will mill down several inches of the current pavement and replace it with new asphalt. It will greatly improve a road surface that has required regular repairs due to the combination of more than 200 freeze-thaw cycles each year and heavy use by commercial vehicles, as well as damage from numerous storms this past winter.

“We’re grateful this much needed project is moving forward,” said Audra Merrick, ADOT’s North Central District engineer. “This project will be the long-term fix to the damage the road has taken over the winter.”

The project also will replace pavement on the on- and off-ramps at the Bellemont interchange, replace guardrail and make minor bridge deck repairs at the Bellemont and A-1 Mountain Road overpasses.

A similar project, slated for the fiscal year beginning July 1, will pick up where this project ends at milepost 179, and continue west for 17 miles to Cataract Lake near Williams.

After pavement damage from powerful and repeated winter storms, ADOT crews continue following up on temporary repairs with asphalt overlays on I-17, State Route 89A in Oak Creek Canyon and other parts of I-40.

ADOT improving Twin Arrows interchange along I-40 east of Flagstaff

FLAGSTAFF – An Arizona Department of Transportation project underway at the Twin Arrows interchange along Interstate 40 just east of Flagstaff will improve access for drivers.

The $4.5 million project between mileposts 218 and 220 will create new eastbound off- and on-ramps, and improve the bridge structure with new girders, wider abutments, a widened and repaved deck, and new safety barriers.

I-40 drivers will encounter a lane restriction in both directions at the interchange as work continues. Access to Twin Arrows Road and I-40 will be maintained, though occasional detours can be expected. Work is expected to be complete by fall.