Blasting resumed in January on State Route 77

PHOENIX – Daytime blasting to remove potentially hazardous rocks resumed yesterday in an effort to protect workers and motorists along State Route 77 south of Globe. SR 77 will be closed in both directions between mileposts 154-161 from 10 a.m. to 3 p.m. every Monday through Thursday.

In addition, lane closures are expected each work day from 7-10 a.m. and from 3-5 p.m. Drivers should expect delays of about 15 minutes during those times. The restrictions are expected to remain in place until March.

ADOT crews had been working at night to remove rocks that could have fallen along SR 77 near Dripping Springs. The work was switched to the safer daylight hours after a loosened 18-foot limestone boulder fell 150 feet and landed on the roadway on November 30.

The incident underscored the risk for construction crews and the potential hazard to motorists. In addition to the instability of the rock face that is being removed, blasting creates flying rock that could be dangerous to workers, especially in the dark between sunset and sunrise.

During the closures, drivers can travel SR 177 and US 60 between Globe and Winkelman. That route will add about 20 miles to the trip.

As with any work zone, drivers are asked to drive slowly and cautiously in the work area and watch for construction workers and equipment.

Out-of-State travelers should be aware that Arizona Revised Statute 28-710 §B. provides for double fines for speeding through a marked highway work zone.

State Route 77 to close for daytime blasting starting December 12

PHOENIX — To protect workers who are blasting potentially hazardous rocks along State Route 77 south of Globe, the Arizona Department of Transportation will close the road for five hours a day, Mondays through Thursdays, for the next four months.

Beginning Monday, December 12, SR 77 will be closed in both directions between mileposts 154-161 from 10 a.m. to 3 p.m. Closures will be in effect Mondays through Thursdays with no closures planned between Monday, December 26, and Tuesday, January 3.

In addition, lane closures are expected each work day from 7-10 a.m. and from 3-5 p.m. During those times, a pilot vehicle will guide motorists through the work zone. Drivers should expect delays of about 15 minutes.

The restrictions are expected to remain in place until March.

ADOT crews have been working at night to remove potentially dangerous rock that could have fallen along SR 77 near Dripping Springs. Work is switching to the safer daylight hours after an 18-foot limestone boulder fell 150 feet during previous nighttime blasting and landed on the roadway on November 30.

The incident underscored the risk for construction crews and the potential hazard to motorists. In addition to the instability of the rock face that is being removed, blasting creates flying rock that could be dangerous to workers, especially in the dark between sunset and sunrise.

During the closures, drivers can travel SR 177 and US 60 between Globe and Winkelman. That route will add about 20 miles to the trip.

As with any work zone, drivers are asked to drive slowly and cautiously in the work area and watch for construction workers and equipment.

SR 77 project to reduce risk of falling rocks dislodges a whopper

sr77-rock_cropAn Arizona Department of Transportation project is blasting rock from a limestone cliff to prevent it from falling onto State Route 77 between Winkelman and Globe.

Illustrating the need, one of the rocks dislodged early Wednesday was far larger than expected, an 18-foot-tall block that dropped onto the highway from 150 feet above and forced crews to keep the route closed four hours longer than scheduled.

Crews on the overnight project worked until nearly 6 a.m. to break up the rock and push it off the highway. As a result, a detour using State Route 177 and US 60 remained the only way around the work area as area residents began their morning commutes.

The project requires working nights under a full closure of SR 77 between mileposts 154 and 161, in the Dripping Springs area, using explosives to remove potentially hazardous rocks from a cliff that hangs over the highway.

ADOT strives to provide timely information on restrictions, closures and detours, but occasionally the unexpected happens and announced schedules aren’t met.

Sometimes rocks break at naturally occurring joints beneath the surface that cannot be seen or anticipated, said J.J. Liu, manager of ADOT’s Geotechnical Services division. When the charge is ignited, it opens the crack at that joint and the rock detaches itself, he said.

Having an unexpectedly large rock come down increases the time needed to remove it, particularly with some of the extremely dense types of rock common in Arizona.

“The mountain is composed of the Mescal Limestone Formation with large blocks of limestone up to 155 feet above the highway, periodically falling with great energy and destructive potential,” said Brent Conner, a senior geotechnical engineer with ADOT.

The nature of the geology in the Dripping Springs area could mean more unanticipated delays before the project is complete, he added.

“The large block that fell required drilling and blasting at the roadway level to remove it from the travel lanes,” Conner said. “Last night’s work was one of the most difficult for the contractor on this project, but a couple more difficult sections remain.”

ADOT to widen seven-mile stretch of Oracle Road in Tucson

adot-logo3PHOENIX – The Arizona Department of Transportation is starting a project that will make it easier for drivers and cyclists to move along a seven-mile stretch of Oracle Road (State Route 77) in the Catalina area.

Beginning June 12, crews will begin adding one new travel lane in each direction for a total of six lanes between Tangerine Road and the Pinal County line. Work will also include widening the shoulders of the road making it easier for cyclists to ride in the area as well as adding raised medians, making traffic signal improvements and installing a shared-use path on the east side of Oracle Road from Wilds Road to Eagle Crest Ranch Boulevard.

Two wildlife crossing structures, one overpass and one underpass, funded by the Regional Transportation Authority, will be constructed as a part of the project. These structures are designed to keep motorists safe and reduce vehicle-animal collisions.

Two lanes of travel will be maintained through the work zone with occasional lane closures taking place during nighttime hours. Drivers are reminded to slow down while traveling through the work zone.

Construction is anticipated to be completed by spring 2016.

Utility relocation work began in spring 2013 to relocate utility lines – including gas, cable, phone and electric – so they won’t be in conflict with the widening project. The utility relocation work will continue through the beginning of the project.

The $33.9 million construction project is a collaboration between the Arizona Department of Transportation, Federal Highway Administration and the Regional Transportation Authority.